Work On New Haven Line’s Catenary System Inches Toward Completion

A new M-8 railcar is hooked up to the overhead catenary wires on the New Haven Line. Photo Credit: Metropolitan Transportation Authority / Patrick Cashin
A Metro-North Railroad train heads for Connecticut on the New Haven Line. Photo Credit: Contributed

FAIRFIELD COUNTY, Conn. – Work to replace the catenary system along the New Haven Line is entering its final phases and is expected to be complete by the middle of 2018.

The State of Connecticut does not allow third rail operations, so trains are powered by overhead wire called catenary, like the kind once seen on trolley cars. Some of the catenary lines being replaced were installed in 1907.

By May, all of the overhead wire and the systems that support them above tracks 3 and 1 along both segments, will have been completed.

June will mark the beginning of the last phase of this project that will replace all the old wires with the new system above tracks 2 and 4. The final portion of work will start first with the Bridgeport to Milford segment, and both segments should be completed by mid-2018.

to sign up for Daily Voice's free daily emails and news alerts.

Welcome to

Newtown Daily Voice!

Serves Bethel & Newtown

Hi! You've read our articles so we know you like our reporting. To keep reading please join our mailing list.

Get important news about your town as it happens.